Citytrain

Indooroopilly Station Upgrade

space
NightLink. Click here for more info.


Indooroopilly Station Upgrade

Project Manager's Update

spacer
spacer spacer spacer spacer spacer

As at 01 October 2008

Progress of works

Recent works include:

Platforms 3 and 4
  • Extension of the platforms are now complete
  • Commenced the final backfill and placement of the paving
  • Continued with the erection of structural steelwork and roofing to the platform shelters


Concourse

  • Continued with the final works to stairs and lift access to Railway Avenue


Subway

  • Continued with major refurbishment works of the subway


External Paving and Roadworks (Railway Ave and Lambert Rd)

  • Continued with excavation, laying of services, backfill and the installation of kerbing

As at 01 September 2008

Progress of works

Recent works include:

Platforms 3 and 4
  • Continued with concrete works for a new stairway to the subway
  • Continued with the installation of concrete foundations to the platform shelters
  • Continued with the erection of structural steelwork and roofing to the platform shelters


Concourse

  • The concourse and lift to Platforms 1 and 2 were opened to the public on 01/09/2008


Subway

  • Subway closed to public on 01/09/2008 to allow for major refurbishment works to commence. For more information refer to the Stage 3 update of the project on this site.

As at 01 August 2008

Progress of works

Recent works include:

Platforms 3 and 4
  • Erection of structural steel to support the roof is complete
  • Roofing progressing 
  • Commencement of concrete works for new stairway to subway
  • Commenced installation of new edging for Platform 4


Concourse

  • Internal fit out of wall framing complete
  • Commenced fit out of station office and equipment
  • Lift installation continuing
  • Work on stairs continuing

As at 02 July 2008

Progress of works

Recent works include:

Platforms 3 and 4
  • Demolition complete
  • Shelter foundations well underway
  • Erection of structural steel columns for shelters is progressing 


Concourse

  • Structural steel work complete
  • Roofing installed
  • Internal fit-out of wall framing almost complete
  • Stairs from concourse to platforms 3 and 4 installed
  • Commenced installation of 2 lifts

As at 26 May 2008

Progress of works

Recent works include:

Platforms 1 and 2
  • Works complete and platforms open to public access


Platforms 3 and 4

  • Platforms closed to public access
  • Demolition commenced


Concourse

  • Continue with the erection of the structural steel work

As at 07 May 2008

Progress of works

Recent works include:

Platforms 1 and 2
  • All structural steel work to the shelters is complete
  • Installation of roof sheeting is well underway
  • Installation of soffit lining (underside of shelters) is underway
  • Placement of asphalt pavement in progress


Concourse

  • Precast floor slabs have been erected and topping slab poured
  • Erection of the precast lift shaft wall panels has commenced

As at 10 April 2008

Progress of works

Recent works include:

  • Completed foundations and columns to stairs, lift shafts and concourse at northern end of platforms 1 and 2 and adjacent to Railway Ave
  • Completed demolition of all structures on platforms 1 and 2
  • Completed foundations and rock anchors to shelters on platforms 1 and 2

As at 23 January 2008

Progress of works

Recent works include:

  • On 07 January, platforms 1 & 2 were closed to passenger trains
  • Commencement of foundation works for columns to construct the stairs, lift shaft and concourse on the north end of platforms 1 & 2 
  • Demolition on platforms 1 & 2 commenced
  • Ticket office commissioned 
  • Column foundations were poured on the corner of Westminster Road bridge and Coonan Street
  • Foundations laid for the columns to construct the lift shaft at Railway Avenue

As at 21 December 2007

Progress of works

Recent works include:

  • Works commenced on the project on 12 November
  • Platforms 3 & 4 were closed to passenger trains
  • Commencement of foundation works for columns to construct the stairs, lift shaft and concourse on the north end of platforms 1 & 2 
  • Temporary 15 m extension of platform 1 & 2 (south end)
  • Excavation work undertaken at the corner of Westminster Road bridge and Coonan Streeet, and scaffolding erected
  • S2K Alliance (Abigroup) site office completed


graphic Need some assistance? Contact Us
City Train
07 3606 5555

Today's Updates
21/11/2008 8:38:07 PM

SERVICE DISRUPTIONS

QR is experiencing service disruptions on the&n...

PEAK TIME RESULTS

Friday 21/11/2008 Trains on time 14...

 Quick Find...

Promotion
Ticket Central, for all the big sport and entertainment events.

  line
Email Email a friend Print Print this page Back to Top Back to top

 
Copyright | Disclaimer | Privacy Statement | Linking to our site | Site Map
QR Passenger Pty Ltd   ACN 132 181 090   ABN 71 132 181 090 - V2
07 3606 5555
spacer